• Removing fill from the site. There will be large dump trucks entering and existing the project daily.

  • Installing the base for the tower-crane 02-13-2023 through 02-24-2023.

  • Pouring tower-crane base concrete on 02-17-2023. There will be concrete trucks entering and existing the site throughout the day, traffic may be held up for short periods.   

  • Delivering and installing tower crane base on 02-14-2023. There will be a mobile crane and large delivery trucks entering and exiting the site during the day.

  • Setting up-assist crane on 02-21-202. There will be large trucks and a crane entering the site, the road will be blocked off for short periods.

  • Installing the tower-crane on 02-23-2023 to 02-24-23. There will be large trucks delivering the crane masts, and parts throughout the day.

  • Ground-breaking ceremony on 02-23-2023 at 10:30 A.M.—Officials from NBV and the Thornton Construction team will be in attendance.